Work has been started , completed 35% of total work in the year of 2022, Remaining work will be completed by June 2023.
]]>Project Information:
Objective(s) | a) To extend High Voltage transmission infrastructure upto northern part of the country for import power in future from India, Nepal and Bhutan. b) To transmit the power from proposed 2×800 MW power plant to be built at Jharkhand, India by Adani Group. |
Scope of Work | a) Construction of Barapukuria-Bogura 400 kV Double Circuit Transmission Line: 120 km b) Construction of Bogura-Kaliakoir 400 kV Double Circuit Transmission Line: 140 km (including 9 km river crossing) c) Construction of 400 kV AIS Bay extension at Kaliakoir 400/230 kV Substation: 2 nos. d) Construction of 230 kV AIS Bay extension at Parbatipur 230 kV Switching Station: 2 nos. |
Project Cost | Total: 405223.00 Lakh BDT GOB: 182208.00 Lakh BDT PA : 205048.00 Lakh BDT PGCB: 17967.00 Lakh BDT |
Development Partner | EXIM Bank of India |
Present Status | Physical : 31.25% Financial : 9.20% |
Estimated Duration | January, 2019 to June, 2024 |
Project Office | Project Director : Sk. Zakiruzzaman, Chief Engineer Mobile : 01755635102 Email : pd.bbkp@pgcb.gov.bd |
Ringtech is Working as sub-contractor of Tata Project Limited.
]]>• To evacuate the power from the upcoming power plants at Ghorasal.
• Up gradation of 230KV transmission network at North-Eastern region of Dhaka.
• To meet the growing demands of greater Dhaka, Chittagong and Sylhet areas.
Up gradation of existing 3 nos of 132KV sub-stations at Comilla (South), Modunaghat (Chittagong) and Manikganj.
Siemens India Ltd. has been awarded this project from Power Grid Company of Bangladesh and Ringtech Ltd. has won Erection, Installation, Testing and Commissioning Works Manikganj 230kV GIS Substation from them.
Ringtech Limited started this project January 2021.
• To evacuate the power from the upcoming power plants at Ghorasal.
• Up gradation of 230KV transmission network at North-Eastern region of Dhaka.
• To meet the growing demands of greater Dhaka, Chittagong and Sylhet areas.
Up gradation of existing 3 nos of 132KV sub-stations at Comilla (South), Modunaghat (Chittagong) and Manikganj.
Siemens India Ltd. has been awarded this project from Power Grid Company of Bangladesh and Ringtech Ltd. has won Manikganj 230kV GIS Bay extension civil Work from Them.
Scope of this project is construction of different equipment foundation, Gantry tower foundation, cable trenches and modification of transformer foundation.
Ringtech Ltd. has started this project in the year of 2020.
As of March, 2021 PGCB has 1 Nos. 2x500MW HVDC Back-to-Back 400kV substation, 3 Nos. 3,120 MVA 400/230kV, 1 Nos. 650 MVA 400/230kV substation, 2 Nos. 1,300 MVA 400/132kV substation, 26 Nos. 14,325 MVA 230/132kV substation, 5 Nos. 1,460 MVA 230/132kV substation. 120 Nos. 23,447 MVA 132/33kV substation, 34 Nos. 5,231.6 MVA 132/33kV substation. And also, PGCB has 26,630 MW dispatch capacity at 33kV level (Including all organizations).
Their vision is “Economic upliftment of the country by reaching electricity to all through reliable transmission”. And mission is “Efficient and effective management of national power grid for reliable and quality transmission of electricity throughout the country”.
Siemens India Ltd. has been awarded “Design, Supply, Erection, Testing & Commissioning of 400/230kV Meghnaghat AIS Substation on Turnkey Basis (Bid Identification No.: PGCB/DCMPGSP/BD-P81/SS/01)” project from PGCB. As a reputed subcontractor of Siemens India Ltd. Ringtech Ltd. has won 400/230kV AIS Meghnaghat Substation Project Bangladesh (Road, Trench, Drain, Gates, Fencing works).
Scope of This project is to construct around 2000m of internal road, cable trenches, surface drain, main gate and fencing.
February 2021, Ringtech started this project.